Builder delayed Rs 44.36L flat by 18 months; RERA orders 10.7% interest

viaTimes of India23 Sept
Builder delayed Rs 44.36L flat by 18 months; RERA orders 10.7% interest
The interest is to be calculated on the amounts already paid by the homebuyer and will apply from June 26, 2025 until the date on which lawful possession of the flat is actually ha